Press conference to update purchasers of Block 1, 3, 7 and 8 Lagoon Perdana together with representatives from MPSJ, MPSJ councillor Tony Chang Kim Loong (also representing House Buyers’ Association) and Mr Ricky Goh of Tenaga Gagah Sdn Bhd (Developer) Below is the article published by NST on 4th June 2010 SUBANG JAYA: After a… Read more »
Posts Categorized: Lagoon Perdana
Updates on Lagoon Perdana (uncompleted units)
Dear purchasers of Lagoon Perdana, For Blocks 1, 3 and 8 Developer has not completed repair works. There are also outstanding assessment and infrastructure fee owing by Developer to MPSJ. TNB meters at every unit has not been installed to the satisfaction of TNB. (I have gone on site with TNB and the Developer last… Read more »
Updates on Lagoon Perdana (uncompleted units)
STATUS TERKINI PROJEK LAGOON PERDANA BLOK 1, 3, 7 & 8 Tuan/Puan, Sukacita saya ingin merujuk kepada e-mail Tuan/Puan yang ditujukan untuk Y.B. Menteri Perumahan dan Kerajaan Tempatan sebelum ini. Untuk makluman Tuan/Puan, mesyuarat terkini bersama wakil syarikat Talam Corporation Berhad (TCB) telah diadakan di Jabatan Perumahan Negara pada 19/5/2010. Tujuan mesyuarat tersebut diadakan adalah… Read more »
Lagoon Perdana (uncompleted units)
This is an email from Jabatan Perumahan Negara:Untuk makluman pihak tuan. wakil dari JPN telah membuat lawatan ke tapak projek ini pada 02/03/2010. Tujuan pemantauan ini dibuat adalah untuk memastikan pemaju menyiapkan projek ini mengikut tarikh jangkaan siap yang diberikan oleh Talam Corporation(TCB) kepada pihak JPN. Hasil daripada lawatan tapak yang diadakan didapati kerja-kerja pemasangan… Read more »
Status of Lagoon Perdana (Uncompleted Units)
This morning I attended a meeting held between representatives of the Developer, MPSJ Councillor Tony Chang, YDP of MPSJ and Perunding Projek Perumahan Terbengkalai Task Force Exco Kerajaan Negeri Selangor. Below is the status update: For Blocks 1, 3 and 8:MPSJ has conducted two inspection at site and has notified the Developer to rectify the… Read more »
Updates on Lagoon Perdana (uncompleted units)
Below is an official reply from Jabatan Perumahan Negara to one of the affected purchasers of the Lagoon Perdana project: Merujuk kepada e-mail Puan yang ditujukan kepada Y.B. Menteri Perumahan dan Kerajaan Tempatan pada tarikh 25/12/2009. Untuk makluman Puan, mesyuarat terkini bersama wakil Syarikat Talam Corporation Berhad (TCB) telah diadakan di Jabatan Perumahan Negara pada… Read more »
Status of Lagoon Perdana (uncompleted units)
Below is the status update I received from the developer of Lagoon Perdana (uncompleted units): Blocks 1 & 8As per the meeting at MPSJ chaired by councillor Mr Ken Chia, we have already passed a copy of the form (to lease the PPU building to TNB) together with a copy of the letter of undertaking… Read more »
Updates on Lagoon Perdana (uncompleted units)
After months of awaiting updates and reply from the developer and Kementerian Perumahan Dan Kerajaan Tempatan (“KPKT”), I finally received the status updates from the developer as stated below (in italic). I was at the site yesterday together with MPSJ councillor Ken Chia to verify the status updates. I will continue to push KPKT to… Read more »
Lagoon Perdana – uncompleted units
On 13 December 2008, the developer for Lagoon Perdana called for a meeting with purchasers of Block 7. The developer briefed the purchasers on the problem faced by them in completing Block 7 (original plan was to build 18 floors, but now the purchasers were informed by the developer that they could only build up… Read more »
Meeting for Block 7 purchasers
I have been informed by the developer, Tenaga Gagah Sdn Bhd that they would be calling for a meeting with all purchasers of Block 7 only of Lagoon Perdana. Notice has been sent out to all Block 7 purchasers. Details of the meeting:- Date: 13 December 2008 Time: 2:30pm Venue: Lagoon Perdana Multi purpose hall