Below is the status update I received from the developer of Lagoon Perdana (uncompleted units):
Blocks 1 & 8
As per the meeting at MPSJ chaired by councillor Mr Ken Chia, we have already passed a copy of the form (to lease the PPU building to TNB) together with a copy of the letter of undertaking to TNB Subang. However there is still no feedback for the approval of the transformers and cabling for the three substations. Works to repair the existing PPU building has commenced.
Block 3
The building works should be finishing by end August and ready for inspection by various authorities by mid September 2009. We have already obtained the approval from Jabatan Kilang dan Keselamatan Perkerja (JKKP) for the lifts and we are arranging Bomba inspection before end August 2009.
Block 7
We are chasing our consultant planner to resubmit for MPSJ Planning approval hopefully by this week. Once the Planning approval is obtained, we will submit our amended building plans for approval. In the mean time we will get ready the various tenders to complete the balance works.
This project is under the supervision of Kementerian Perumahan Dan Kerajaan Tempatan (“KPKT”). I will continue to push for regular updates from the developer.