Please find below the status update on Lagoon Perdana uncompleted units by the purchasers’ representative:
For BLKS 1, 3, & 8 – works are in full swing
Blk 1 & 8 – to be delivered by end Dec 08 /Jan 09
Blk 1 & 8 – to be delivered by end Dec 08 /Jan 09
Blk 3 – to be delivered by end of Feb 09/Mac 09
Blk 7 – still waiting on 2nd opinion from the consultant. the first consultant informed to go ahead with progress work but however TGSB/IJMC referred to 2nd consultant
Blk 1 & 8 – work is going on till 9pm
Blk3 – work is progressing well
I’m following up closely for Blk 7, with KPKT, TGSB/IJM, whereby the 2nd opinion should be reverted to them by end of this month